Current decision

Keep the facility under review.

The first 300 kW is forecast to arrive 14 days early. The second 300 kW is forecast 44 days late, with switchgear commissioning still open. Both blocks need confirmed usable dates and hold terms before the buyer commits.

If 1 September is fixed
Ask for another facility that can support both phases on the required dates.
If the rollout can move
Decide whether starting with 15 racks justifies waiting for the second block. Reassess once the operator updates its date and hold terms.

Two equal phases. One deadline at risk.

Illustrative dates for usable power in 2027
PhaseBuyer needsOperator expectsAgainst target
First 300 kW15 June1 June14 days early
Next 300 kW1 September15 October44 days late
Buyer requirement
One facility, with two phases of 15 air-cooled racks at 20 kW each. Total IT load reaches 600 kW.
Operator’s written response
The operator forecasts both blocks at one facility. Phase two depends on switchgear commissioning. Reservation terms remain open for both phases.

What needs to happen next.

Confirm the power date.
Operator commissioning lead · by

Send a dated switchgear update and the earliest date the full second 300 kW can be tested and usable.

Set out the hold terms.
Operator commercial team · before any commitment

State what would reserve each block, which approvals are needed and when each hold would expire.

Choose the rollout path.
Buyer deployment lead · once written terms and dates arrive

Record whether the September deadline can move. Compare an alternate single facility against a revised schedule at this site.

Use your browser’s print command to save a copy of this fictional brief.